MSB (55 / 54)
E_0249 — Check order issuance for metering location change
Check order issuance for metering location change
| Attribute | Value |
|---|---|
| Designation | Check order issuance for metering location change |
| Market role | MSB |
| Regulatory determination / chapter | WiM electricity |
| Section | 8.6.1: AD: Metering location change from NB to MSB |
| Check identifiers | Response: 19005, 19006 |
| EBD version | 4.2 |
| As at | 2026-06-23 |
Decision tree
| Step | Check | Result | Code | Note |
|---|---|---|---|---|
| 1 | Is the requested change date at least 20 WT after the message receipt date? | no | A01 | Cluster: Rejection Deadline not met |
| — | — | yes | A02 | Cluster: Consent The change can be carried out. |
Result codes
| Result code | Cluster | Meaning | Response check identifier |
|---|---|---|---|
A01 | Rejection | Deadline not met | 19006 |
A02 | Consent | Change can be carried out. | 19005 |
Notes on this page
Role of the numbers: »response« are the check identifiers that list this tree in the ebd_code column of the check identifier table (knowledge-collection · FV 202604); »checked« is the difference set to it from the return path of the process steps. The »response check identifier« column of the result codes assigns a cluster only because this tree carries exactly one checked message and exactly one response per pole; their pole comes from the use case title of the response.
Not checked against a process
No consistency check was carried out for this decision tree — no generated BPMN found. Whether the MACO APP implements this tree completely is therefore not evidenced here.