MSB (55 / 54)
E_0283 — Check order placement
Check order placement
| Attribute | Value |
|---|---|
| Designation | Check order placement |
| Market role | MSB |
| Regulatory determination / chapter | Processes for changing the technical equipment at locations |
| Section | 8.2.2: AD: Metering location change from LF to MSB |
| Check identifiers | Response: 19005, 19006 |
| EBD version | 4.3 |
| As at | — |
Decision tree
| Step | Check | Result | Code | Note |
|---|---|---|---|---|
| 10 | Does the requested technology already exist at the location? | yes | A01 | Cluster: Rejection Ordered technology is already in place. |
| — | — | no | → Step 20 | — |
| 20 | Is the MSB still the assigned MSB at the affected location at the start of the requested implementation period? | yes | → Step 30 | — |
| — | — | no | A02 | Cluster: Rejection MSB is no longer assigned to the affected location at the start of the implementation period. |
| 30 | Is the requested technology fundamentally possible at the affected location? | yes | → Step 40 | — |
| — | — | no | A03 | Cluster: Rejection The requested technology is not possible at the location concerned. |
| 40 | Is implementation of the requested technology fundamentally possible within the specified implementation period? | yes | → Step 50 | — |
| — | — | no | A04 | Cluster: Rejection Implementation is not possible within the requested implementation period. Note: An alternative implementation period must be stated. |
| 50 | Can the specified price sheet be accepted in the specified version? | yes | → Step 60 | — |
| — | — | no | A05 | Cluster: Rejection The stated price sheet cannot be accepted in the stated version. |
| 60 | Has a previously unspecified error occurred? | yes | A99 | Cluster: Rejection Other Note: The identified problem must be described/named in the response. End of usability: 01.04.2027 00:00 |
| — | — | no | A06 | Cluster: Consent Send order confirmation. |
Result codes
| Result code | Cluster | Meaning | Response check identifier |
|---|---|---|---|
A01 | Rejection | The ordered technology is already in place. | 19006 |
A02 | Rejection | MSB is no longer assigned to the affected location at the start of the implementation period. | 19006 |
A03 | Rejection | The requested technology is not possible at the affected location. | 19006 |
A04 | Rejection | Implementation is not possible within the requested implementation period. Note: An alternative implementation period must be specified. | 19006 |
A05 | Rejection | The specified price sheet cannot be accepted in the specified version. | 19006 |
A99 | Rejection | Other Note: The identified problem is to be described/named in the response. End of usability: 01.04.2027 00:00 | 19006 |
A06 | Consent | Send order confirmation. | 19005 |
Notes on this page
Role of the numbers: »response« are the check identifiers that list this tree in the ebd_code column of the check identifier table (knowledge-collection · FV 202610); »checked« is the difference set to it from the return path of the process steps. The »response check identifier« column of the result codes assigns a cluster only because this tree carries exactly one checked message and exactly one response per pole; their pole comes from the use case title of the response.
Not checked against a process
No consistency check was carried out for this decision tree — no generated BPMN found. Whether the MACO APP implements this tree completely is therefore not evidenced here.